Project History
A new I-5 crossing
Since the late 1990s, Clark County planning efforts have consistently reflected the need for new I-5 crossings north of NE 134th Street . Locations from NE 139th Street to NE 219th Street were considered to relieve traffic congestion on the existing I-5 crossings and improve connections between neighborhoods.
As growth projections in the area changed and computer traffic modeling technology improved, traffic projections in the Salmon Creek area were refined making the need for a new I-5 crossing near NE 134th Street increasingly clear. No other option, including widening NE 134th Street, relieved congestion enough to meet county traffic standards on NE 134th Street.
Interchange options considered
Since 2002, the Salmon Creek Interchange Project team considered many ways to provide access to I-5 from the Salmon Creek area. Preliminary designs were compared based on criteria that included accommodating forecasted traffic demand; minimizing right-of-way impacts, potential environmental impacts, and project cost; and meeting community expectations. Through this process, a full interchange at NE 139th Street was identified for further study in the environmental assessment.
Revised project design
Additional design and environmental study continued through early 2006 when more detailed information about the selected design led to increases in the original cost estimate. The project team discovered additional risks and needs as environmental, design and traffic studies progressed which resulted in increased costs. These findings included:
- increases in traffic volumes forecasted over the next twenty years
- evidence that the C-Tran Park-and-Ride needed to be relocated to allow NE 134 th Street to operate at an acceptable level
- presence of high ground water, poor soil conditions, and a sensitive wetland in key construction areas
- significant cost increases for construction materials, particularly steel, asphalt, pipe and concrete
- significant increases in real estate values, which affect purchase prices of properties needed for road rights-of-way

